Corte Madera Parks Reopening: Menke Park & Town Park Playground

Three of Corte Madera's public spaces are being rebuilt in the same twelve months. Menke Park reopened in September. The Town Park playground, closed since 2024, appears as an opening item on the Parks and Recreation Commission's agenda. A permanent home for the town's all-ages programs is going into the former Andy's Market space on Tamal Vista Boulevard. Corte Madera sales tax revenue covers part of the cost of two of the three, and for the Intergenerational Center it covers most of it.

Menke Park came back first

The Town held a grand reopening for the newly renovated Menke Park on Saturday, September 19, with a 2 to 4 p.m. ribbon-cutting and ice cream social. Lappert's donated the ice cream, and Rocky Road featuring Sal, Rich and friends played. The Corte Madera Community Foundation sponsored the afternoon.

The Town's construction notice from March listed the scope:

  • An ADA-accessible path linking the upper and lower areas of the park
  • A low retaining wall that also works as informal seating
  • New benches and a full replacement of the irrigation system
  • Native landscaping
  • Roof, paint and railing work on the Piccolo Pavilion

That notice put construction from the week of April 6 through mid-July, weather permitting. The park reopened about two months after that window closed. For anyone who read our August note on the concert series that never moved back to Menke this summer, the pavilion is finished and the series has a renovated stage for next season.

Menke also drew on private fundraising. The Corte Madera Community Foundation worked with landscape architect Sara Cohen and the Town's Engineering Department, focusing on safe access, new stairs, compliant pathways and tree work. The Foundation calls the campaign its most ambitious fundraising project to date.

The playground at Town Park, designed with kids' votes

The Town Park playground was built in the early 2000s. It was boarded up in 2024 after a town inspection found it unsafe, according to the Marin Independent Journal. That leaves the town's main park without a play structure for well over a year, in a spot next to the Cove parking lot that families from both Corte Madera and Larkspur use.

On December 16, 2025, the Town Council unanimously approved a $335,000 replacement from GameTime, an equipment maker based in Fort Payne, Alabama. A July 2025 survey drew 142 responses, mostly from Corte Madera and Larkspur residents who visit the park every week. The Town then turned the comments into two concept designs and let children choose between them. Parks and Recreation Director Tim Barry told the Marin Independent Journal, "They actually loved the exercise and got really into it."

The chosen design includes slides, a butterfly-shaped climbing structure, stepping stones and a combined spinning and climbing feature. The project's state environmental filing describes poured-in-place resilient surfacing and reuse of certified mulch.

The Town received a grant of nearly $83,000 in July 2025 from a program supported by the California Parks and Recreation Society and playground design companies, and it had to order the equipment by the end of 2025 to use it. Aside from the grant, the Marin Independent Journal reported, most of the project costs would come from about $150,000 in sales tax revenue and $180,200 from the Town's recreation capital fund.

The Commission's October 26 agenda packet lists "Town Park Playground Opening" among staff updates, the same heading used at its September 28 meeting. The Town has not posted a ribbon-cutting the way it did for Menke. Before you plan a weekend morning around it, check with Corte Madera Parks and Recreation on whether the fence is down.

A permanent room for a program that lost its old one

The third project is indoors, and its financing depends on the sales tax more than either park's does.

According to the Southern Marin Ledger, Age-Friendly Intergenerational Solutions will move into a renovated 3,100-square-foot space at 195 Tamal Vista Boulevard. That is the former Andy's Market storefront in the Bell Mt. Tam center. The nonprofit has offered free fitness, art and social classes to older adults in Corte Madera and Larkspur since 2018. Its original center opened at the Corte Madera Community Center on April 29, 2018, and closed in 2020. The Ledger reports that the town has had no dedicated space for older-adult programs since then.

The Town signed a five-year lease with property owner BCF 1 Tam Ridge LP on November 6, 2025. The Council authorized a construction contract of up to $360,000 plus a 10% contingency. The finished building will have:

  • A lobby
  • A flexible-use room with movable seating and dividers
  • A 600-square-foot activity room
  • A small meeting room
  • An ADA-accessible bathroom
  • An outdoor patio and 14 dedicated parking spaces
  • An office for the Corte Madera Chamber of Commerce

The opening date has moved. A March 2026 Town staff report estimated four months of construction and an October 2026 opening. Administrator Carla Condon told the Larkspur Community Foundation in an August 31 interview, as reported by the Southern Marin Ledger, that she looks forward to seeing the center open in January 2027.

Who paid for what

Project Approved or contracted amount Funding sources reported Status as of late October 2026
Menke Park and Piccolo Pavilion Not published Community Foundation campaign working with Town Engineering Reopened September 19
Town Park playground $335,000 Grant of nearly $83,000, plus about $150,000 sales tax and $180,200 recreation capital fund "Opening" listed as a Commission staff update
Intergenerational Center, 195 Tamal Vista Blvd. Up to $360,000 plus 10% contingency $342,400 Measure F sales tax, $43,600 landlord tenant-improvement allowance, $10,000 Rotary donation Opening expected January 2027

About $150,000 of the playground money came from sales tax revenue. For the Intergenerational Center, Measure F sales tax provides $342,400 of about $396,000 in total funding, and the landlord and Rotary cover the rest. In a town with two regional shopping centers, Corte Madera Town Center and The Village at Corte Madera, sales tax revenue pays directly for the places where residents spend their weekday afternoons.

What's next on the list

  1. Outdoor fitness equipment. The Town's Community Outdoor Fitness Equipment survey drew 172 responses, 30 more than the playground survey, and the Commission told staff to put the equipment in the 2027 Work Plan.
  2. Town Park East Field. The renovation carries $320,000 in the Commission's project tables, and East Field updates are a standing staff report item with a dedicated ad hoc subcommittee.
  3. The 2027 facilities list. The Commission began discussing possible 2027 projects on October 26, and final recommendations come back on December 17.

Earlier in the year, the Commission's 2026 recommendations also named connections to Town Park Plaza, new picnic tables and benches, and new bocce courts. December 17 is the meeting to watch for which of those survive into next year.

The holiday season at the two centers

The same two shopping centers whose sales tax helps fund these projects have their own holiday calendars through the end of the year.

At Corte Madera Town Center, the 34th annual food drive opens November 5 and runs through January 1. Nonperishable donations for the San Francisco-Marin Food Bank go to the Giant Turkey near Arhaus. The Wednesday farmers market runs 11 a.m. to 5 p.m. in the center court. Asian Box opened at 147 Corte Madera Town Center Drive on September 19, in the former Veggie Grill space, according to the Press Democrat.

Across the freeway, The Village at Corte Madera hosts the Field & Flowers Community Market on Saturday, November 7, starting at 11 a.m. Its St. Vincent de Paul Society of Marin clothing drive runs November 20 through December 24, and Pet Nights with Santa run November 23 through December 14. The Village's holiday page offers Santa photos by reservation or walk-in.

Upgrades to parks and community buildings change what a block is like to live on, and they come up in conversations with buyers. If you're considering a sale near Menke Park, Town Park or Tamal Vista Boulevard and want to know how these projects figure in a buyer's view of your street, Domain SF Marin would be glad to meet with you and prepare a personalized home valuation.

Work With Us